    Project Scheduling with Simultaneous Optimization, Time, Net Present Value, and Project Flexibility for Multimode Activities with Constrained Renewable Resources

    (ندگان)پدیدآور
    Farughi, HAmiri, AAbdi, F
    Thumbnail
    دریافت مدرک مشاهده
    FullText
    اندازه فایل: 
    1.573 مگابایت
    نوع فايل (MIME): 
    PDF
    نوع مدرک
    Text
    زبان مدرک
    English
    نمایش کامل رکورد
    چکیده
    Project success is assessed based on various criteria, every one of which enjoys a different level of importance for the beneficiaries and decision makers. Time and cost are the most important objectives and criteria for the project success. On the other hand, reducing the risk of finishing activities until the predetermined deadlines should be taken into account. Having formulated the problem as a multi-objective planning problem, the present study aims at minimizing the project completion time as well as maximizing the net present value and project flexibility by taking into account the resource constraints and precedence relations. Here the flexibility of project is calculated by considering a free float for each activity and maximizing the sum of these flotation times. Although most of the researches considered the resources as non-renewable resources, here the resources are considered as renewable ones. Moreover, performing each activity may be possible in various states of using resources (mode) which can change the project completion time and cost. Owing to the complexity of the problem, the Multi Objective Simulated Annealing Meta-heuristic Algorithm is used to solve the proposed model. In doing so, first a feasible answers is proposed and then, using the aforementioned algorithm, it was attempted to find Pareto answers. For accrediting the algorithm, four benchmark problems have been considered. Since the algorithm performed well in finding the optimal answers to the benchmark problems, it was used to find the optimal answer of large scale problems.
    کلید واژگان
    Resource constrained project scheduling
    time
    cost trade
    Off
    Simulated Annealing meta
    Heuristic Algorithm
    Project flexibility
    multi
    mode activities

    شماره نشریه
    5
    تاریخ نشر
    2018-05-01
    1397-02-11
    ناشر
    Materials and Energy Research Center
    سازمان پدید آورنده
    Faculty of Engineering, University of Kurdistan, Sanandaj, Iran
    Faculty of Engineering, University of Kurdistan, Sanandaj, Iran
    Faculty of Engineering, University of Kurdistan, Sanandaj, Iran

    شاپا
    1025-2495
    1735-9244
    URI
    http://www.ije.ir/article_73180.html
    https://iranjournals.nlai.ir/handle/123456789/336947

    مرور

    همه جای سامانهپایگاه‌ها و مجموعه‌ها بر اساس تاریخ انتشارپدیدآورانعناوینموضوع‌‌هااین مجموعه بر اساس تاریخ انتشارپدیدآورانعناوینموضوع‌‌ها

    حساب من

    ورود به سامانهثبت نام

    آمار

    مشاهده آمار استفاده

    تازه ترین ها

    تازه ترین مدارک
    © کليه حقوق اين سامانه برای سازمان اسناد و کتابخانه ملی ایران محفوظ است
    تماس با ما | ارسال بازخورد
    قدرت یافته توسطسیناوب