    Return on Investment in Transmission Network Expansion Planning Considering Wind Generation Uncertainties Applying Non-dominated Sorting Genetic Algorithm

    (ندگان)پدیدآور
    Abbasi, S.Abdi, H.
    Thumbnail
    دریافت مدرک مشاهده
    FullText
    اندازه فایل: 
    764.3کیلوبایت
    نوع فايل (MIME): 
    PDF
    نوع مدرک
    Text
    Research paper
    زبان مدرک
    English
    نمایش کامل رکورد
    چکیده
    Although significant private investment is absorbed in different sectors of power systems, transmission sector is still suffering from appropriate private investment. This is because of the pricing policies of transmission services, tariffs, and especially for investment risks. Investment risks are due to the uncertain behaviour of power systems that discourage investors to invest in the transmission sectors. In uncertain environment of power systems, a proper method is needed to find investment attractive transmission lines with high investment return and low risk. Nowadays, wind power generation has a significant portion in total generation of most power systems. However, its uncontrollable and variable nature has turned it as a main source of uncertainty in power systems. Accordingly, the wind power generation can play a fundamental role in increasing investment risk in the transmission networks. In this paper, impact of this type of generation on investment risk and returned investment cost in transmission network is investigated. With different levels of wind power penetration, the recovered values of investment cost and risk cost in transmission network are calculated and compared. This is a simple method to find investment attractive lines in presence of uncertainties. Wherein, transmission network expansion planning (TNEP) is formulated as a multi-objective optimization problem with objectives of minimizing the investment cost, maximizing the recovered investment cost and network reliability. The point estimation method (PEM) is used to address wind speed variations at wind farms sites in the optimization problem, and the NSGA II algorithm is applied to determine the trade-off regions between the TNEP objective functions. The fuzzy satisfying method is used to decide about the final optimal plan. The proposed methodology is applied on the IEEE 24-bus RTS and simplified Iran 400 kV network.
    کلید واژگان
    Point Estimation Method
    Private Investment
    Transmission Network Expansion Planning
    Wind power Generation
    NSGA II algorithm
    Planing & Reliability

    شماره نشریه
    1
    تاریخ نشر
    2018-06-01
    1397-03-11
    ناشر
    University of Mohaghegh Ardabili
    دانشگاه محقق اردبیلی
    سازمان پدید آورنده
    Razi University
    Razi University (Kermanshah)

    شاپا
    2322-4576
    2423-4567
    URI
    https://dx.doi.org/10.22098/joape.2018.3867.1303
    http://joape.uma.ac.ir/article_640.html
    https://iranjournals.nlai.ir/handle/123456789/232952

    مرور

    همه جای سامانهپایگاه‌ها و مجموعه‌ها بر اساس تاریخ انتشارپدیدآورانعناوینموضوع‌‌هااین مجموعه بر اساس تاریخ انتشارپدیدآورانعناوینموضوع‌‌ها

    حساب من

    ورود به سامانهثبت نام

    آمار

    مشاهده آمار استفاده

    تازه ترین ها

    تازه ترین مدارک
    © کليه حقوق اين سامانه برای سازمان اسناد و کتابخانه ملی ایران محفوظ است
    تماس با ما | ارسال بازخورد
    قدرت یافته توسطسیناوب